ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!

  • google app store apple app store
  • тЬЦ

      Question

      If 'A' needs 24 more days to complete a certain task

      working alone compared to when 'A' and 'B' work together, and 'A' is 50% more efficient than 'B', what is the amount of time 'B' takes to finish the same task on their own?
      A 95 days Correct Answer Incorrect Answer
      B 20 days Correct Answer Incorrect Answer
      C 30 days Correct Answer Incorrect Answer
      D 90 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let the time taken by 'A' to finish the work alone be '2x' days. Ratio of efficiencies of 'A' and 'B' = 3:2 Since, the work done is same, ratio of efficiencies of 'A' and 'B' will be inverse of the ratio of time taken by 'A' and 'B' to finish the work. So, time taken by 'B' to finish the work alone = 2x ├Ч (3/2) = '3x' days So, time taken by 'A' and 'B' to finish the work together = (2x - 24) days ATQ: (1/2x - 24) = (1/3x) + (1/2x) or, (1/2(x - 12)) = (2x + 3x)/(2x ├Ч 3x) or, 3x = 5 ├Ч (x - 12) or, 3x = 5x - 60 or, 2x = 60 x = 30 So, time taken by 'B' to finish the work alone = 3x = (30 ├Ч 3) = 90 days

      Practice Next
      More Time and work Questions
      ask-question