Question
Akhil and Nikhil together can complete a work in 10 days
while Nikhil alone takes 20 days to complete 40% of the work. If the efficiency of Sachin is 25% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.Solution
Time taken by Nikhil to complete the whole work alone = 20/0.40 = 50 days Let the total work = 50 units Efficiency of (Akhil + Nikhil) = 50/10 = 5 units/day Efficiency of Nikhil = 50/50 = 1 units/day Efficiency of Akhil = 5 - 1 = 4 units/day Therefore efficiency of Sachin = 1.25 x 4 = 5 units/day Time taken by Sachin to complete the whole work alone = 50/5 = 10 days
 Consider the following statements:
1.The Constitution (74th Amendment) Act, 1992 provides for the constitution of Wards Committees.
2.Th...
Find the HCF of 245, 175 and 385.
In classical dance, which of the following Rasa represents "anger"?
A minimum rate of remuneration which shall be applied to an employee working on piece work for the purpose of securing to such employees a minimum rate...
What do we call the force which affects the direction of wind and is caused by the rotation of the earth on its axis?
Who among the following was added to advisory board to PM CARES Fund in September, 2022?
The Lucknow Pact was signed in ______ by Congress and the Muslim League to work in alliance for representative government.
Dargah of which following Sufi Saint is not located in India?
URL stands for:
 The “Hunga Tonga Hunga Haapai” volcano eruption was huge and loud in the ________ region of Tonga island?