Question
Abhijeet' is 50% less efficient than 'Vivek' and can
achieve 25% of the sales target in 8 days.'Chirag' takes 4 days more than 'Vivek' to achieve the target. Which of the following statements is/are true according to the given information? I. 'Abhijeet' and 'Chirag' together can achieve 81.25% of the target in 10 days. II. 'Vivek' and 'Chirag' together can complete 90% of the target in 8 days. III. 'Abhijeet' takes 12 days more than 'Chirag' to complete the target alone.Solution
ATQ, Time taken by ‘Abhijeet’ to achieve the target alone = 8/0.25 = 32 days Time taken by ‘Vivek’ to achieve the target alone = 0.5 × 32 = 16 days Time taken by ‘Chirag’ to achieve the target alone = 16 + 4 = 20 days Let the total target achieved be 160 units Efficiency of ‘Abhijeet’ = 160/32 = 5 units/day Efficiency of ‘Vivek’ = 160/16 = 10 units/day Efficiency of ‘Chirag’ = 160/20 = 8 units/day For statement I: Time taken by ‘Abhijeet’ and ‘Chirag’ together to achieve 81.25% of the target = 0.8125 × (160/13) = 10 days Therefore, statement I is true. For statement II: Time taken by ‘Vivek’ and ‘Chirag’ to achieve 90% of the target together = 0.9 × (160/18) = 8 days Therefore, statement II is true. For statement III: Time taken by ‘Abhijeet’ is 12 days more than ‘Chirag’. Therefore, III is true.
Nikhil and Rohit together can complete a job in 105 days 8 minutes, while Rohit and Suresh together can finish the same job in 70 days 5 minutes. If Sur...
Worker 'A' can complete the entire task in 35 hours, and Worker 'B' can complete it in 40 hours, when working individually. If both 'A' and 'B' work tog...
A and B together can complete a piece of work in 35 days while A alone can complete 50% of the work in 20 days. Find the time taken by B to complete 12....
Two workers, ‘X’ and ‘Y’, can finish a job in 25 days together. If ‘X’ is 25% more efficient than ‘Y’, find the number of days ‘Y’ a...
Shivam and Harish can do a job alone in 90 days and 120 days respectively. Both work together and earn Rs. 5,250. Find Shivam’s earnings.
A and B finish a job together in 36 days, while B and C together finish it in 48 days. The trio completes 75% of the job in 18 days. In how many days wi...
Anil, Sunil, and Rajesh can complete a project working alone in 6, 8, and 12 days, respectively. If they all work together to complete the project and e...
8 children and 6 women together can complete a piece of work in 10 days and work done by a children in one day is one-third of the work done by a women ...
A’ and ‘B’ together can complete a work in 22 days while ‘A’ takes 33 days to complete the same work alone. If ‘C’ is 20% more efficient t...
- Meena alone can complete a work in 20 days. Ritu is twice as efficient as Meena. Find the percentage of work completed by Meena and Ritu together in 4 days...