Question
Ashish and Anil can do a piece of work in 12 days and 15
days respectively. Ashish completed 30% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 12 and 15) = 60 units Efficiency of Anil = 60/15 = 4 units/day Remaining work = 60 x 0.7 = 42 units Time taken by Anil to complete the remaining work = 42/4 = 10.5 days
In the context of a lease, what is the term used for the transferee?
As laid down under the Exim Bank Act the Central Government may advance to the Exim Bank a loan of _______________ at a rate of interest of five and a q...
Which one of the following is NOT available as a remedy against an ex parte decree?
The court may frame the issues from the materials:Â
A re-examination of a case for lack of jurisdiction made by a higher court is?
When a witness is cross-examined, he may be asked questions which tend:
Which of the following is a constitutional body ?
For compensation for wrongful seizure of movable under legal process, the period of limitation as per provisions of Limitation Act 1963, to file suit is:
The chairman and vice chairman of Central Board constituted under Employees’ Provident Fund are appointed by _______________.
Which Act was repealed and replaced by the Competition Act, 2002?