      Question

      Ashish and Anil can do a piece of work in 12 days and 15

      days respectively. Ashish completed 30% of the work. Find the time taken by Anil to complete the remaining work.
      A 10.5 days Correct Answer Incorrect Answer
      B 4.5 days Correct Answer Incorrect Answer
      C 9 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer

      Solution

      Let the total work be (LCM of 12 and 15) = 60 units Efficiency of Anil = 60/15 = 4 units/day Remaining work = 60 x 0.7 = 42 units Time taken by Anil to complete the remaining work = 42/4 = 10.5 days