Question
A can do a piece of work in 28 days, while B can do the
same piece of work in 42 days. They begin working together and 6 days before completion of work, A leaves. Find the total number of days taken to complete the work.Solution
Suppose the work finished in x days. A' s one day work is 1/28 day B's one day work is 1/42 day According to the question, Let the total work was done in x days then, A works for (x - 6)days Then, (x - 6)/28 + x/42 = 1 3x – 18 + 2x = 84 5x = 102 x = 102/5 days. Alternate Method: A B 28 42 let total work = LCM of 28 & 42 = 84 units So Eff : 3 : 2 So in last 6 days B worked alone so his work in last 6 days = 2`xx` 6 = 12 units So remaining work = 84-12 = 72 units Hence A & B will do it in = 72/5days Hence total days = 72/5 +6 = 102/5 days
How many terms are there in the geometric progression 6, 18, 54, 39366?
There are two natural numbers such that the square of the smaller number exceeds five times the larger number by 4. Additionally, the sum of these two n...
Find the remainder obtained when 34 × 46 × 52 is divided by 25.
The cube of the difference between two given natural numbers is 1728, while the product of these two given numbers is 108. Find the sum of these two giv...
Let x = (726)245 – (437)458 + (333)335. What is the unit digit of x?
N is the largest two digit number, which when divided by 3, 4 and 6 leaves the remainder 1, 2 and 4 respectively. What is the remainder when N is divid...
Find the average of first 25 whole numbers.
- The average of five consecutive numbers is 23. Find the middle number.
Out of a certain number of books, 2/5 are novels and the rest are textbooks. If the number of textbooks is 36, find the total number of books.
Sum of three positive numbers is 160. If the ratio of the first and second number is 2:3, respectively while difference between the first and third numb...