Question

A can do a piece of work in 28 days, while B can do the same piece of work in 42 days. They begin working together and 6 days before completion of work, A leaves. Find the total number of days taken to complete the work.

A 91/5 days.
B 102/5 days.
C 81/5 days.
D 64/5 days.
E None of these
Practice Next

More Time and work Questions

Hey! Ask a query