Question
A can do 1/4th of a work in 15 days, B can do the 25% of the work in 20 days & C can do 1/5th of the work in 15 days. Who will complete the work first?
More Time and work Questions
- A and B together can do a piece of work in 15 days which B and C together can do in 20 days. After A has been working at it for 3 days and then by B for 11...
- 28 men can complete a work in 20 days. 40 women can complete the same work in 28 days. 20 men and 12 women started working and after 16 days, 20 more women...
- Sudhanshu completes `1/3` of work in 12 days, then he completes the remaining work with the help of Neeraj in 4 days. The time required for Neer...
- A buffalo alone can plough field ‘A’ in 30 days. A Bull alone can plough the field ‘A’ in 50 days. Find the number of days taken by 2 bulls and 1 buffalo t...
- 24 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 8 hours a day for 24 ...
- 'Zara' is capable of finishing a specific task in 60 days. On the other hand, 'Armaan' takes 40% more time than 'Zara' to complete the same task, while 'Ta...
- Machine X is 100% more efficient than Machine Y, and Machine Y is 75% more efficient than Machine Z. Machines X and Z, working together, can complete a cer...
- 'X', 'Y', and 'Z' can complete a job individually in 20 days, 30 days, and 24 days respectively. 'Y' and 'Z' begin the task together. After 6 days, 'Z' lea...
- A 210 litres mixture contains only water and phenyl in the ratio 3:2, respectively. If 60 litres of this mixture is replaced with 100 litres of alcohol, th...
- A and B together can finish a work in 10 days. Their rates of working are in the ratio 2 : 3. In how many days can each of them finish the work alone?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt