Question
5 girls can do a piece of work in 9 days, 4 boys can do
the same piece of work in 8 days, 6 men do the same piece of work in 2 days and 4 women can do the same piece of work in 4 days. Who is least efficient?Solution
5 girls can do a piece of work = 9 days 1 girl can do a piece of work = 9 × 5 = 45 days. 4 boys can do a piece of work = 8 days 1 boy can do a piece of work = 4 × 8 = 32 days. 6 men can do a piece of work = 2 days 1 men can do a piece of work = 6 × 2 = 12 days. 4 women can do a piece of work = 4 days 1 woman can do a piece of work = 4 × 4 = 16 days. Hence, girls are least efficient.
The power of buyers will increase when:
Which of the following is an attribute of selling?
Which of the following statements is true about Facebook?
Which of the following is an example of non-durable goods?
When a marketer thinks that there is a demand for the product in the market but in reality, there is isn’t, it is known as _______ demand.
What is the main difference between advertising in traditional print media and advertising on Facebook?
Alarm clock is an example of _________ demand, as its demand is reducing with time.
The process of defining a marketing problem and opportunity, systematically collecting and analyzing information, and recommending actions to improve an...
Facebook, Amazon.in, Expedia.com, and Dell.com are all examples of:
why might a new company decide to target 60 years old as opposed to 40 years old?