📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      P and Q can separately finish the work in 15 days and 25

      days respectively. They worked together and P left the work, so Q complete the remaining work in 5 days. After how many days P left the work?
      A 11/2 days Correct Answer Incorrect Answer
      B 15/2 days Correct Answer Incorrect Answer
      C 6 days Correct Answer Incorrect Answer
      D 7/2 days Correct Answer Incorrect Answer

      Solution

      P can do a work in 15 days. Q can do a work in 25 days. Let P left after x days. Q worked for (x+5) days. ∴ 1/15 × x + 1/25 (x+5) = 1 x/15 + x/25 + 1/5 = 1 (5x+3x)/75 = 4/5 8x/75 = 4/5 x = 15/2 days  Alternate method: Let total work = LCM(15, 25) = 75  So P’s 1 day work = 5 & Q’s 1 day work =3 So Q’s 5 days work in last  = 3×5 = 15  So remaining work  = 75 – 15 = 60 So this 60 units of work is completed by both in = 60/(5+3) = 60/8 = 15/2 days

      Practice Next
      ask-question