Question
A man can complete a job alone in 20 days. A woman can
complete half of the same job in 15 days. If both work together, how many days will it take them to complete 80% of the job?Solution
ATQ,
Time taken by the woman to finish the entire work = 15 ÷ 0.5 = 30 days
Let the total work be 60 units. {LCM of (20 and 30)}
So, efficiency of the man = 60 ÷ 20 = 3 units/day
And efficiency of the woman = 60 ÷ 30 = 2 units/day
So, required time = (60 × 0.8) ÷ (3 + 2) = 9.6 days
A team of 'x' boys can complete a job in 18 days if they all work together. However, every day, 15 boys leave the team after star...
- 22 men can finish a piece of work in 20 days, while 44 women can do the same job in 30 days. How many days will 1 man and 1 woman take to complete the work...
P and Q can do a piece of work in 32 and 40 days respectively. They began to work together but P leaves after sometimes and Q completed remaining work i...
Virat can do a piece of work in 20 days and Sachin can do the same work in 30 days. If Virat works for 4 days and got Rs. 2400, and the remaining work w...
‘A’ alone can complete a work in 50 hours. ‘A’ started the work alone and left after working on it for 20 hours. If ‘B’ completed the rest o...
X can work as fast as Y and Z together. X and Y together can finish the same task 3 times as fast as Z. If all three working together can finish the tas...
In a Construction site Men, Women and Children were working in the ratio 6:3: 1 to finish a job and their individual wages were in the ratio 3:1:2. Enti...
P’s 5 days work is equal to Q’s 6 days work. If P and Q together can complete the work in 25 days then how much time Q will take to complete 80% of ...
A and B together can complete a piece of work in 55 days while B and C together can complete the same work in 66 days. All of three togeth...
A can fabricate a divider in 30 days , while B alone can assemble it in 40 days, If they construct it together and get an installment of Rs 7000, then f...