Question
A man can complete a job alone in 20 days. A woman can
complete half of the same job in 15 days. If both work together, how many days will it take them to complete 80% of the job?Solution
ATQ,
Time taken by the woman to finish the entire work = 15 ÷ 0.5 = 30 days
Let the total work be 60 units. {LCM of (20 and 30)}
So, efficiency of the man = 60 ÷ 20 = 3 units/day
And efficiency of the woman = 60 ÷ 30 = 2 units/day
So, required time = (60 × 0.8) ÷ (3 + 2) = 9.6 days
In case of mutually exclusive projects and when NPV and IRR giving conflicting results, go for the project having higher IRR
In which of the following state Nag River flow?
राजस्थान के किस जिले में सर्वाधिक लिंगानुपात है ?
Where and when was the Ghadar Party founded?
How many states do the biodiversity-rich Western Ghats span across in India?
The first Football World Cup final was played between:
1. Every year the annual meeting of World Economic Forum is held in Davos. It is a cityin:
Which cities does the first Namo Bharat Rapid Rail connect?
Who is the International Chess Federation (FIDE) Deputy President?
Who will take charge as director of cricket at the National Cricket Academy (NCA) in Bengaluru?