A and B can complete a task in 63 days and 42 days,
respectively. If C is 40% more efficient than the combined efficiency of A and B, how much time will C take to complete the entire task?Solution
Let total amount of work = 126 units (LCM of 63 and 42) Efficiency of A = 126/63 = 2 units per day Efficiency of B = 126/42 = 3 units per day Efficiency of C = 1.40 Γ 5 = 7 units per day Desired time = 126/7 = 18 days
Which of the following private sector bank has launched two new products β loan against deposits and dollar bonds β for non-resident Indians at its ...
What is the sectoral exposure limit for UCBs with respect to real estate, including commercial real estate, as a percentage of total assets?
Consider the following Statements and choose the option with correct Statements.
I- PM Kisan is a Central Sector Scheme to supplement the finan...
Consider the following statements regarding Pradhan Mantri Jan Aarogya Yojana (PM-JAY):
I. It targets the beneficiaries as identified by Socio-...
Which of the following is considered as a Non-Banking Financial Company (NBFC)?
Agriculture Infrastructure Fund (AIF) is a financing facility operational from the year 2020-21 to ____________ for the creation of post-harvest managem...
What would be the profit as per cash basis of accounting based on the following information:
Revenues on account = Rs.50000
Cash Sales =...
In the January 2024 circular on bulk deposits, which tier of UCBs has a revised bulk deposit threshold set at βΉ1 crore?
A person who is reliable, dependable, goal oriented and well organised is high on which of the following personality traits?
Eligible participants/issuers for Commercial Paper shall obtain credit rating for issuance of CP from any one of the SEBI registered CRAs. The minimum c...