A and B can complete a task in 63 days and 42 days,
respectively. If C is 40% more efficient than the combined efficiency of A and B, how much time will C take to complete the entire task?Solution
Let total amount of work = 126 units (LCM of 63 and 42) Efficiency of A = 126/63 = 2 units per day Efficiency of B = 126/42 = 3 units per day Efficiency of C = 1.40 × 5 = 7 units per day Desired time = 126/7 = 18 days