Question
A and B can complete a task in 63 days and 42 days,
respectively. If C is 40% more efficient than the combined efficiency of A and B, how much time will C take to complete the entire task?Solution
Let total amount of work = 126 units (LCM of 63 and 42) Efficiency of A = 126/63 = 2 units per day Efficiency of B = 126/42 = 3 units per day Efficiency of C = 1.40 Ă— 5 = 7 units per day Desired time = 126/7 = 18 days
Social networks are
During the maturity stage of the product life cycle, profit declines because:
Which of the following statements about e-commerce is true?
Direct selling involves ______ active customer involvement and _______ active retailer involvement.
Someone making the statement, "Before we begin this project, we'll have to hire someone to interview people to find out how many people in a 50-mile rad...
A new start-up recently finished prototyping their invisiblity gown, and they are now available at select retailers across the country. What stage of th...
A form of ownership that involves multiple outlets under common ownership is known as a(n):
Online media where users submit news, photos, and videos—often accompanied by a feedback process to identify "popular" topics—are referred to as
...The rising trend of Facebook growth alongwith betterment of internet facilities and smartphone connectivity is an example of ____________ forces.
At a recent executive meeting, the marketing manager said: "starting tomorrow, we will Tweet five times a day!" This decision is an example of a(n):