Question
Reena and Teena together can do a piece of work in 60 days. Teena and Meena together can do it in 40 days. Reena starts the work and works on it for 10 days, then Teena takes up work for 30 days. Finally Meena finishes the work in 36 days. The number of days in which Meena alone can do the work where doing separately is
More Time and work Questions
- A started a work such that he can complete the whole work in 30 hours. After working for 10 hours, he worked with the rate such that the whole work can be ...
- A and B can complete a task together in 26 days, while B alone takes 52 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- Avinash is twice as good as Bhuvanesh and together they can finish a job in 50 days. Bhuvanesh will finish the work alone in how many days?
- A alone can complete 50% of a work in 10 days while B takes 8 days more than A to complete it. If B and C together can complete the work in 12 days, then f...
- Sudhanshu completes `1/3` of work in 12 days, then he completes the remaining work with the help of Neeraj in 4 days. The time required for Neer...
- ‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 12 days and after that ‘N’ is replaced by ‘M’. If the total work is completed...
- A and B together can finish a work in 10 days. Their rates of working are in the ratio 2 : 3. In how many days can each of them finish the work alone?
- Neil and Oscar together can build a wall in 24 days. Neil takes five times as long as Oscar to build the wall alone. Find the time taken by Oscar to build ...
- ‘R’ and ‘S’ can complete an assignment in 72 days and 90 days respectively while ‘R’, ‘S’ and ‘T’ together can complete the same assignment in 24 days. Fin...
- 'Meera', 'Kiran', and 'Suman' together can complete a work in 30 days. 'Meera' and 'Kiran' together can complete the same work in 90 days. 'Suman' alone ca...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
According to the question, Reena = 10 Teena = 10 + 20 Meena = 20 + 16 Work Done by (Reena + Teena) in 10 days = 2 × 10 = 20 units Work Done by (Teena + Meena) in 10 days = 3 × 20 = 60 units Total work (Finished till now) = 80 units Remaining Work = 120 – 80 = 40 units Here we find that Meena does remaining 40 units in 16 days Meena’s efficiency = work/day = 40/16 = 5/2 Therefore, time taken by Meena alone to complete the work = 120 × `2/5` = 48 days