Question

A can do a work in 12 days and B in 16 days. If they work on it together for 3 days then in how many days the remaining work will be completed by B?

A 9 days
B 5 days
C 7 days
D 4 days
E 2 days
Practice Next

More Time and work Questions

Hey! Ask a query