Question
A can do a work in 12 days and B in 16 days. If they
work on it together for 3 days then in how many days the remaining work will be completed by B?Solution
Total work = Number of days × 1 day’s work (efficiency) Total work = LCM (12, 16) = 48 unit 1 day’s work of A = 48/12 = 4 unit 1 day’s work of B = 48/16 = 3 unit 1 day’s work of (A + B) = 4 + 3 = 7 unit Now, 3 day’s work of (A + B) together = 3 × 7 = 21 unit Remaining work = 48 – 21 = 27 Remaining work completed by B = 27/3 = 9 days
What is the purpose of a transistor in a circuit?
What are the three main dimensions of big data known as the "3Vs"?
Virtual memory allows for the efficient management of:
Out of star schema and snowflake schema, whose dimension table is normalized?
What does A/B testing involve in data analytics?
What is the output of the following code?
print(min(max(False,-30,-4), 12,7))
What is the purpose of the finally block in exception handling?
What does a crow's foot notation represent in an ER diagram?
What does a "hash" represent in the context of blockchain?
In tuple calculus, what does the β symbol represent?