Question
A can do a work in 12 days and B in 16 days. If they
work on it together for 3 days then in how many days the remaining work will be completed by B?Solution
Total work = Number of days × 1 day’s work (efficiency) Total work = LCM (12, 16) = 48 unit 1 day’s work of A = 48/12 = 4 unit 1 day’s work of B = 48/16 = 3 unit 1 day’s work of (A + B) = 4 + 3 = 7 unit Now, 3 day’s work of (A + B) together = 3 × 7 = 21 unit Remaining work = 48 – 21 = 27 Remaining work completed by B = 27/3 = 9 days
SSNM aims at supplying
Consider the following stages:
1. Spore germination      Â
2. Embryo infection
3. Spore on flower grain
4. Infected g...
Organisms of which division under Kingdom Plantae are called the Amphibians of the Plant Kingdom?
The meat is the good culture media for the growth of microorganisms due to
The fertilizer phosphorus use efficiency under optimum condition is
The finest and most popular variety of Mandarin orange
The chairman of the state variety release committee
The first ever wheat variety for conservation agriculture in India is
We can cut the DNA with the help of
Sterilization by use of irradiation is also called