Question
A can do a work in 12 days and B in 16 days. If they
work on it together for 3 days then in how many days the remaining work will be completed by B?Solution
Total work = Number of days × 1 day’s work (efficiency) Total work = LCM (12, 16) = 48 unit 1 day’s work of A = 48/12 = 4 unit 1 day’s work of B = 48/16 = 3 unit 1 day’s work of (A + B) = 4 + 3 = 7 unit Now, 3 day’s work of (A + B) together = 3 × 7 = 21 unit Remaining work = 48 – 21 = 27 Remaining work completed by B = 27/3 = 9 days
Statements:Â Some documents are files.
All books are folders.
No file is a folder.
Conclusions: Â Â Â Â Â I. No folder is ...
In this question, three statements are given, followed by three conclusions numbered I, II and III. Assuming the statements to be true, even if they s...
In the question below are given some statements followed by some conclusions. You have to take the given statements to be true even if they seem to be ...
In the question below some statements are given followed by two conclusions I, and II. You have to take the given statements to be true even if they se...
- Statements:
Some Hands are Fingers
Some Fingers are Toes
All Toes are Lips
Conclusion:
I. Some Fingers are Lips ... - In the question below some statements are given followed by three conclusions I, II and III. You have to take the given statements to be true even if they ...
Statements:
No pen is pencil.
Some pencil is eraser.
All eraser is box.
Some box is scale.
 Conclusions:
...
- Read the given statements and conclusions carefully. Assuming that the information given in the statements is true, even if it appears to be at variance wi...
Statements:
Some kitchen is balcony.
No balcony is room.
Some room is floor.
All floor is roof.
Conclusions:
...Statements:
All present are past
 Some past are future
Only a few future is tense
Conclusions:
I. Some tense can ne...