Question
30 workers putting in 8 hours a day finish a task in 10 days. How many days will it take for 20 workers working 12 hours daily to finish the same task?
More Time and work Questions
- ‘A’ and ‘B’ together can complete a work in 8 days, while ‘B’ and ‘C’ together can complete the work in 10 ...
- A can count 100 eggs in 4 minutes while B can count the same number of eggs in 5 minutes. How much time will be required if they work together to count 450...
- Neha and Priya are assigned a piece of work. Neha can complete 8 units of work each day, while Priya can finish the whole task alone in 32 days. If the tot...
- P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 10 t...
- 'Ramesh' can complete a work in 40 days. He started the work and left after 24 days from starting. The remaining work was done by 'Suresh' in 30 days. Find...
- ‘X’ and ‘Y’ together can complete a work in 12 days, while ‘Y’ and ‘Z’ together can complete the work in 10 days. If ‘Y’ takes 10 days to complete the work...
- A team of 12 men and 18 women can complete a construction project in 24 days. If 6 women alone can do the same project in 144 days, how many days will 48 m...
- A, B, and C can finish a job in 12, 15, and 18 days, respectively. They collaborate to complete the task and receive a combined payment of Rs. 592 for thei...
- A is 20% more efficient than B. How much time will they working together take to complete a job which A alone could have done in 29 days?
- A and B can complete a task together in 12 days, while B alone takes 24 days to finish it. A began working alone and left after ‘x’ days, after which B com...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt