Question
‘X’ and ‘Y’ together can do a work in 16 days. If ‘X’ increases his efficiency by 75% and ‘Y’ decreases his efficiency by 25%, then the time taken to complete the work remains unchanged. Find the ratio of efficiencies of ‘X’ and ‘Y’, respectively.
More Time and work Questions
- X can finish a task in 20 days, while Y can do it in 25 days. If Z needs 1.2 times the time taken by X and Y together, find the number of days Z will take ...
- A buffalo alone can plough field ‘A’ in 20 days. A Bull alone can plough the field ‘A’ in 10 days. Find the number of days taken by 1 bulls and 4 buffalo t...
- A and B together, B and C together and A and C together can complete a piece of work in 80 days, 60 days and 70 days respectively. Find the ratio of the ef...
- 40 laborers were hired to finish a construction job in 50 days. After 35 days of work, only 62.5% of the job was done. How many additional laborers are nee...
- ‘A’, ‘B’ and ‘C’ can complete a piece of work in 60 days, 120 days and 80 days respectively. ‘A’ and ‘B’ started the work together but ‘A’ left the work af...
- Q can do a work in 15 days and R can do the two-third work done by P and Q together in a day. If R completes the work in 18 days, how many days will it tak...
- Rohan can finish a task alone in 24 days. Shreya can do 50% of the same task alone in 12 days. If Shreya and Tanya work together, they can complete 60% of ...
- If Pawan can do a piece of work in 6 days and Mantu can complete the same work in 2 days, then in how many days will both of them together complete the wor...
- A and B together can complete a job in 2 days. A alone takes x + 6 days to complete the job, while B alone takes x + 24 days to complete the same job. 1.W...
- A can complete a work in 10 days, B in 15 days and C in 30 days. All three work together for 2 days. Then B leaves. In how many more days will A and C fini...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)