      Question

      β€˜X’ and β€˜Y’ together can do a work in 16 days.

      If β€˜X’ increases his efficiency by 75% and β€˜Y’ decreases his efficiency by 25%, then the time taken to complete the work remains unchanged. Find the ratio of efficiencies of β€˜X’ and β€˜Y’, respectively.
      A 1:2 Correct Answer Incorrect Answer
      B 2:1 Correct Answer Incorrect Answer
      C 3:1 Correct Answer Incorrect Answer
      D 4:3 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Let the efficiency of β€˜X’ and β€˜Y’ be β€˜x’ units/day and β€˜y’ units/day, respectively. So, total work = {(x + y) Γ— 16} units After change in efficiencies, Also, total work = (1.75x + 0.75y) Γ— 16 So,
      1.75x + 0.75y = x + y Or,
      0.75x = 0.25y Or,
      x : y = 3 : 1 So, ratio of efficiency of β€˜X’ and β€˜Y’ = 3 : 1