Question
‘X’ and ‘Y’ together can do a work in 16 days. If ‘X’ increases his efficiency by 75% and ‘Y’ decreases his efficiency by 25%, then the time taken to complete the work remains unchanged. Find the ratio of efficiencies of ‘X’ and ‘Y’, respectively.
Solution
Let the efficiency of ‘X’ and ‘Y’ be ‘x’ units/day and ‘y’ units/day, respectively. So, total work = {(x + y) × 16} units After change in efficiencies, Also, total work = (1.75x + 0.75y) × 16 So,
1.75x + 0.75y = x + y Or,
0.75x = 0.25y Or,
x : y = 3 : 1 So, ratio of efficiency of ‘X’ and ‘Y’ = 3 : 1
More Time and work Questions
- Pooja is twice as efficient as Nita and four times as efficient as Kavya. If Nita takes 30 days to finish some work, then find the time taken by Pooja and ...
- P and Q can complete a work in 26 days and 39 days, respectively. P, Q and R together can complete the work in 13 days. If R get a total wage of Rs. 5850 t...
- A can complete a piece of work in 80 days, B takes 20% more time than A to complete the same work while C takes 25% more time than B to complete the whole ...
- A piece of work consists of 360 identical units. A can do (x + 4) units per day and B can do (x − 2) units per day. They work together for 9 days and the r...
- The efficiency of C is 20% more than the efficiency of D. D alone can complete a piece of work in (y-2) days. The time taken by C alone to complete the wor...
- ‘A’ alone can complete a work in 10 days. ‘B’ alone can complete the same work in 20 days. If ‘A’ and ‘B’ work together for 3 days, then the remaining work...
- 20 men can do a task in 18 days while 30 women can complete the same task in 24 days. In how many days will 1 man and 1 woman complete it together?
- ‘A’ alone can complete a piece of work in 30 days while ‘A’ and ‘B’ together can complete the same work in 20 days. ‘B’ started the work and after 4 days ‘...
- Anil and Ashish receive Rs.1200 for work of 8 days. If Anil is 5 times efficient than Ashish, then find the daily wage received by Ashish.
- ‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 20 days and after that ‘N’ is replaced by ‘M’. If the total work is completed...