Question
Ram can do a piece of work in 12 days and Shyam can do
the same work in 16 days. They both started work together, Ram left 2 days before the completion of work. Then the total work is completed in how many days?Solution
Required Answer = [((16-2) ×12 )/(12+16) ] + 2 = (14 × 12)/28 + 2 = 8 days Alternate method: Ram can do a job in 12 days & Shyam can do same job in 16 days. Let assume total work = LCM (12, 16) = 48 units So Ram can daily do = 48 / 12= 4 units & Shyam can do daily = 48/ 16 = 3 units So Ram left 2 days before the completion of work ,it means that Shyam worked alone in last 2 days Hence Shyam did in last 2 days = 3× 2 = 6 units So remaining work = 48 – 6 = 42 is done by both Hence they worked together initially for = 42/(4 + 3) = 42 / 7 = 6 days Hence total days for completing the work = 6 days + 2 days = 8 days
1219.98 ÷ 30.48 × 15.12 = ? × 2.16
What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.)...
`1804/898-:99/699xx749/751=?`
(√845 ×19.932+ √4230 ×14.385)/(√1765 ×4.877 ) = ?
Direction: Please solve the following expression and choose the closest option
`(13.022)^(2)+ (42.93)^(2)-(53.125)^(2)+(192.33xx14.88)=?- (88.44)^(2)- (42.03 xx 23.12)`
√49 + 6.66% of 1725 + 22² = ?² - √361Â
What approximate value will replace the question mark (?) in the following?
? =...
? = 49.97% of 38.09% of 1998.95
- What approximate value will come in place of the question mark (?) in the following question? (Note: You are not expected to calculate the exact value.)