Question

    Ram can do a piece of work in 12 days and Shyam can do

    the same work in 16 days. They both started work together, Ram left 2 days before the completion of work. Then the total work is completed in how many days?
    A 6 days Correct Answer Incorrect Answer
    B 10 days Correct Answer Incorrect Answer
    C 8 days Correct Answer Incorrect Answer
    D 9 days Correct Answer Incorrect Answer

    Solution

    Required Answer = [((16-2) ×12 )/(12+16) ] + 2 = (14 × 12)/28 + 2 = 8 days Alternate method: Ram can do a job in 12 days & Shyam can do same job in 16 days. Let assume total work = LCM (12, 16) = 48 units So Ram can daily do = 48 / 12= 4 units & Shyam can do daily = 48/ 16 = 3 units So Ram left 2 days before the completion of work ,it means that Shyam worked alone in last 2 days Hence Shyam did in last 2 days = 3× 2 = 6 units So remaining work = 48 – 6 = 42 is done by both Hence they worked together initially for = 42/(4 + 3) = 42 / 7 = 6 days Hence total days for completing the work = 6 days + 2 days = 8 days

    Practice Next