Question
Ram can do a piece of work in 12 days and Shyam can do
the same work in 16 days. They both started work together, Ram left 2 days before the completion of work. Then the total work is completed in how many days?Solution
Required Answer = [((16-2) ×12 )/(12+16) ] + 2 = (14 × 12)/28 + 2 = 8 days Alternate method: Ram can do a job in 12 days & Shyam can do same job in 16 days. Let assume total work = LCM (12, 16) = 48 units So Ram can daily do = 48 / 12= 4 units & Shyam can do daily = 48/ 16 = 3 units So Ram left 2 days before the completion of work ,it means that Shyam worked alone in last 2 days Hence Shyam did in last 2 days = 3× 2 = 6 units So remaining work = 48 – 6 = 42 is done by both Hence they worked together initially for = 42/(4 + 3) = 42 / 7 = 6 days Hence total days for completing the work = 6 days + 2 days = 8 days
Insurance is listed in which schedule of the Indian constitution ?
The section of the policy that outlines what is NOT covered is called:
Which one of the following does not belong to the main products of life insurance?
A wide range of ICT services including Nationwide Communication Network for decentralised planning, improvement in Government services and wider transpa...
Event covered under insured’s policy agreement is called?
What is meant by customer lifetime value? Â
A Mutual Fund’s SIP is essentially a staggered payment over a defined period of time with a defined contribution by the investors. What is the expansi...
The maximum foreign direct investment (FDI) allowed in Indian insurance companies is:
A policy that covers the loss of stock due to refrigeration failure is:
Which of the following pools is managed by GIC?