Question
Ram can do a piece of work in 12 days and Shyam can do
the same work in 16 days. They both started work together, Ram left 2 days before the completion of work. Then the total work is completed in how many days?Solution
Required Answer = [((16-2) ×12 )/(12+16) ] + 2 = (14 × 12)/28 + 2 = 8 days Alternate method: Ram can do a job in 12 days & Shyam can do same job in 16 days. Let assume total work = LCM (12, 16) = 48 units So Ram can daily do = 48 / 12= 4 units & Shyam can do daily = 48/ 16 = 3 units So Ram left 2 days before the completion of work ,it means that Shyam worked alone in last 2 days Hence Shyam did in last 2 days = 3× 2 = 6 units So remaining work = 48 – 6 = 42 is done by both Hence they worked together initially for = 42/(4 + 3) = 42 / 7 = 6 days Hence total days for completing the work = 6 days + 2 days = 8 days
Statements:
P < Q < R < S ≤ B < H; S > N ≥ Y
Conclusions:
I) P < Y
II) R ≥ N
In the question, assuming the given statements to be true, find which of the conclusion (s) among given three conclusions is/are definitely true and the...
Statements: P ≥ Q ≥ R = S, Q ≥ T > U ≥ V
Conclusion:
I. P ≥ V
II. P > V
Statements: J < K; L = M; K >N ≥ L
Conclusions:
I. J < L
II. N = M
Statements: M = N ≤ P = C > G, D ≥ M > T = F
Conclusion:
I. D ≥ N
II. N > F
III. F < P
Statements: A ≥ B ≥ Y = Z = M ≥ N ≤ E ≤ F = J
Conclusions:
I. F > Z
II. J ≤ Y
Which of the following expression symbols should replace the question mark(?) in the given expressions to make the expression C ≥ E as well as D > M d...
Statement: M < N; L ≥ U; L ≥ Q; U > N ≥ T
Conclusion:
I. N > Q
II. Q > T
Statements: X < H = U ≤ I < N = M, M > B ≥ V
Conclusions:
I. I > V
II. U ≥ MStatement: D > C > U < K > E > N < A
Conclusion:
I. D > N
II. D > A