Question
A and B can complete a job together in 30 days; B and C
can complete the same job together in 25 days, while C and A can complete the same job together in 10 days. In how many days will A, B, and C be able to complete the same job alongside D, who is only 75% as efficient as C?Solution
A+B= 30 B+C=25 C+A=10days LCM of 30, 25, and 10 = 150 A+B B+C C+A 30 25 10 150 5 6 15 Total 2(A+B+C) = 5+6+15+=26 A+B+C =13 C = 13-5 =8 D= 8×75/100 =6 NOW A+B+C+D = 13+6=19 SO total days = 150/19 =7(17/19) days
Which Excel function is used to count the number of cells in a range that meet specified criteria?
Which of the following is the Shortcut key for Find?
The document can be zoom maximum upto
To make the selected text bold, the shortcut key is ____
In MS Excel 365, which of the following is an example of absolute reference pointing to cell A1?
Which formatting feature in MS Word 365, is used to emphasise text by making it bold, italic or underlined in documents?
Which of the following file format can be added to a PowerPoint show?
Turn on _____, which allows word to break lines between the syllables of words.
Which one of the following shortcut key is used to insert a page break?
Which shortcut key is used to center-align text in Microsoft Word?