Question
A and B can complete a job together in 30 days; B and C
can complete the same job together in 25 days, while C and A can complete the same job together in 10 days. In how many days will A, B, and C be able to complete the same job alongside D, who is only 75% as efficient as C?Solution
A+B= 30 B+C=25 C+A=10days LCM of 30, 25, and 10 = 150 A+B    B+C     C+A 30       25       10           150  5         6       15 Total 2(A+B+C) = 5+6+15+=26 A+B+C =13 C = 13-5 =8 D= 8×75/100 =6 NOW A+B+C+D = 13+6=19 SO total days = 150/19 =7(17/19) days
The edible part of the member of Lilliaceae family i.e. Asparagus officinalis is
What is the minimum concentration of fruit pulp/ Juice in the ideal squash?
What method is recommended for the extraction of papain from papaya fruits?
Banana is propagated by
Bitter pit in Apple is due to the deficiency of _________
____ is a milk process that makes milk more easily digested by those with a sensitive digestive system.
What is the preferred pH range for growing orchids?
What is the term for the method used to separate leaf pigments in green plants?
Which of the following is used as rootstock for sapota?
Bending is guava is done to favour: