A and B can complete a work in 18 hours. A leaves the work after 6 hours. B takes 36 hours to complete the remaining work. If A works alone. then how many hours will it take him to finish the work?

A 54 Days
B 45 Days
C 21 Days
D 27 Days
E None of these