Question

Ram and Shyam are partners in completing a project. Ram can finish the project in 42 days, while Shyam can complete it in 54 days. Both began the project together, but Ram had to stop after 21 days, leaving Shyam to finish the project by himself. How many days did it take to complete the entire project?

A 26 days
B 27 days
C 28 days
D 24 days
E None of these