Question
βAβ is 40% more efficient than βBβ. βAβ and βBβ work together for 8 days after which βAβ is replaced by βCβ. βBβ and βCβ together take 4 more days to finish the work. If βAβ alone couldβve finished the whole work in 20 days, then find the time taken by βCβ to finish 60% work alone.
Solution
Let the efficiency of 'B' be 'x' units/day So, efficiency of 'A' = x Γ 1.4 = '1.4x' units/day Total work = 20 Γ 1.4x = '28x' units So, work done by 'A' and 'B' together in 8 days = (x + 1.4x) Γ 8 = '19.2x' units So, remaining work = 28x - 19.2x = '8.8x' units So, efficiency of 'B' and 'C' together = 8.8x Γ· 4 = '2.2x' units per day So, efficiency of 'C' = 2.2x - x = '1.2x' units/day So, required time = (28x Γ 0.6) Γ· 1.2x = 14 days
- 15 men can do a piece of work in 10 days working 12 hours a day. How many men can do double the work in 25 days working 8 hours a day?
- 'P', 'Q', and 'R' can complete a job in 60, 90, and 120 days respectively. They begin together, but 'P' leaves 10 days before the work is done and 'Q' leav...
- A contractor hired 50 workers to complete a work in 80 days. After 50 days, it was found that only 1/4th of the work was completed. Find the number of extr...
- 10 machines can produce 25 items in 5 hours. How long will 8 machines take to produce 40 items?
- The ratio of time taken by P, Q and R to complete work alone is 4:5:2 respectively. If all three together complete the work in 8 days, then find in how man...
- P alone can finish a piece of work ‘M’ in 8 days while Q takes 4 days to finish it alone. P, Q and R working together can finish the work &lsqu...
- Arun and Bala, alone can complete a work in 20 days and 30 days, respectively. They started the work together and left after 8 days such that the remaining...
- Working 6 hours a day, Rahul can complete a work in 25 days. How many hours a day should he work to complete the same work in 15 days?
- Komal and Seema individually can complete a task in β4aβ hours and β8aβ hours respectively. If they together can complete half of the work in 8 hours, then...
- A group of 36 boys works 13 hours per day and completes 37.5% of a task in 20 days. After these 20 days, 'X' boys leave the job. The remaining boys continu...