📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      ‘A’ is 80% more efficient than ‘B’. ‘A’ and ‘B’ work together for 5 days after which ‘A’ is replaced by ‘C’. ‘B’ and ‘C’ together take 10 more days to finish the work. If ‘A’ alone could’ve finished the whole work in 20 days, then find the time taken by ‘C’ to finish 60% work alone.

      A 14 days Correct Answer Incorrect Answer
      B 12 days Correct Answer Incorrect Answer
      C 15 days Correct Answer Incorrect Answer
      D 18 days Correct Answer Incorrect Answer
      E 24 days Correct Answer Incorrect Answer

      Solution

      Let the efficiency of 'B' be 'x' units/day So, efficiency of 'A' = x × 1.8 = '1.8x' units/day Total work = 20 × 1.8x = '36x' units So, work done by 'A' and 'B' together in 5 days = (x + 1.8x) × 5 = '14x' units So, remaining work = 36x - 14x = '22x' units So, efficiency of 'B' and 'C' together = 22x ÷ 10 = '2.2x' units per day So, efficiency of 'C' = 2.2x - x = '1.2x' units/day So, required time = (36x × 0.6) ÷ 1.2x = 18 days

      Practice Next
      More Time and work Questions

      Relevant for Exams:

      ask-question