Question
It takes a team of either 20 boys or 35 girls, 27 days
to achieve a sales target. How many days will it take for a team consisting of 21 boys and 42 girls to complete the entire sales target?Solution
ATQ, Let efficiency of a boy and a girl be 'b' units/day and 'g' units/day, respectively. According to question, 20b = 35g 4b = 7g Total amount of targets = 20b × 27 = 540b units 21 boy and 42 girls = 21b + 42g = 21b + 6 × 7g = 21b + 24b = 45b Hence Desired time = (540b/45b) = 12 days
Which of the following is a weakest acid?
What is a 'double fault' in tennis?
Which British scientist is known for developing the principle of holography in 1947 to improve the resolution of the electron microscope?
Which city topped the Global Smart City Index 2024?
Approximately how much percentage (nearest to integer) of total water on the surface of earth is accounted for by the oceans?
Which of the following organization releases the World Silver Survey annually?
A Ghatam is a ______.
Prime Minister Narendra Modi recently presented four BHISHM Cubes to the Government of Ukraine. What is the capacity of each BHISHM Cube in terms of han...
Which state in India has the highest urban population as on 2019?
Dr.Teejan Bai, a Padma Shri, Padma Bhushan and Padma Vibhushan awardee is globally recognised for her contribution to which of the following art forms?