Question
Rohit and Mohit began a job together, but after 10 days
Rohit left the task. Mohit finished the rest of the job alone in 8 days. Rohit is 40% less efficient than Mohit. If they earned Rs. 3600 for completing the work, find Mohit’s share.Solution
ATQ,
Let the efficiency of Mohit be 5x units/day
So, efficiency of Rohit = 5x × (60/100) = 3x units/day
Work done in first 10 days = 10 × (3x + 5x) = 80x units
Work done by Mohit in 8 days = 8 × 5x = 40x units
Total work = 80x + 40x = 120x units
Work done by Mohit = 10 × 5x + 8 × 5x = 90x units
So, Mohit's share = (3600 / 120x) × 90x = Rs. 2700
Which of the following is not a functional area in which SPS deals?
Dying declaration was recorded by the Judicial Magistrate but the declarant survived. In this case______
No attachment under a precept shall continue for more than_____
For the purpose of section 363-A of Indian Penal Code, 1860, 'Minor' means:-
In the context of a contract for the sale of unascertained goods, when does the property in the goods transfer to the buyer?
According to section 96 of the Companies Act the annual general meeting of an unlisted company may be held at any place in India if ________________
As per the LLP Act where the Tribunal makes an order under section 60 sanctioning a compromise or an arrangement in respect of a limited liability partn...
According to the Central Vigilance Commission Act, 2003 the Central Vigilance Commissioner, the other Vigilance Commissioners and the Secretary to the C...
What is the age of majority of a person domiciled India in as per the Majority Act, 1875?
How many proviso are there to Section 92 of Evidence Act?