Question
Rohit and Mohit began a job together, but after 10 days
Rohit left the task. Mohit finished the rest of the job alone in 8 days. Rohit is 40% less efficient than Mohit. If they earned Rs. 3600 for completing the work, find Mohit’s share.Solution
ATQ,
Let the efficiency of Mohit be 5x units/day
So, efficiency of Rohit = 5x Ă— (60/100) = 3x units/day
Work done in first 10 days = 10 Ă— (3x + 5x) = 80x units
Work done by Mohit in 8 days = 8 Ă— 5x = 40x units
Total work = 80x + 40x = 120x units
Work done by Mohit = 10 Ă— 5x + 8 Ă— 5x = 90x units
So, Mohit's share = (3600 / 120x) Ă— 90x = Rs. 2700
What is the main objective of the $23 million loan agreement between India and the Asian Development Bank (ADB)?
Veteran Telugu actor Kota Srinivasa Rao passed away at what age?
Which country has unveiled a five-year plan to become an innovation hub for the global robotics industry by 2025?
 In the construction of the Ram Mandir in Ayodhya, what traditional building practices have been followed, and what material has been avoided in the st...
Bharatiya Reserve Bank Note Mudran Ltd (BRBNML) is located in?
Which countries are included under the UPI Global Acceptance feature of Bank of Baroda’s bob इ Pay app?
Who inaugurated India’s first tempered glass manufacturing plant, and where is it located?
What was the growth in core sector output in May 2025, the lowest in nine months?Â
Bank of Baroda (BoB) has made a prudential provision of Rs 500 crore for exposure to Go First, which has sought bankruptcy protection after the National...
The “Swachh Kurukshetra – Mera Kurukshetra, Mera Abhimaan” cleanliness mission launched by the Haryana CM is scheduled to run for how many weeks a...