      Question

      A team of workers can finish a task in 36 days. However, 5

      workers leave the task every day, and it gets done in 48 days. Find the time needed for 90 workers to complete the task working together.
      A 125 Correct Answer Incorrect Answer
      B 188 Correct Answer Incorrect Answer
      C 225 Correct Answer Incorrect Answer
      D 195 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let the number of workers be 'W' and each has efficiency 'e' units/day.

      Total work = W Γ— 36 Γ— e = 36We units.

      ATQ:

      36We = W Γ— e + (W - 5 Γ— 1) Γ— e + (W - 5 Γ— 2) Γ— e + .... + (W - 5 Γ— 47) Γ— e

      Or,

      36W = 48W - 5 Γ— (1 + 2 + 3 + .... + 47)

      β‡’ 12W = 5 Γ— 47 Γ— (48/2)

      β‡’ W = (5 Γ— 47 Γ— 24) Γ· 12 = 470

      Let the required time be T days for 90 workers.

      So, 36 Γ— 470 Γ— e = 90 Γ— T Γ— e

      β‡’ T = (36 Γ— 470) Γ· 90 = 188