ATQ,
Let the number of workers be 'W' and each has efficiency 'e' units/day.
Total work = W × 36 × e = 36We units.
ATQ:
36We = W × e + (W - 5 × 1) × e + (W - 5 × 2) × e + .... + (W - 5 × 47) × e
Or,
36W = 48W - 5 × (1 + 2 + 3 + .... + 47)
⇒ 12W = 5 × 47 × (48/2)
⇒ W = (5 × 47 × 24) ÷ 12 = 470
Let the required time be T days for 90 workers.
So, 36 × 470 × e = 90 × T × e
⇒ T = (36 × 470) ÷ 90 = 188
How many persons sit between Sonu and Sunny?
Which of the following fruit does S like?
Whose anniversary is falling earlier than that of anyone else in the group?
How many boxes are kept above the box with White?
Six trucks with codes – A1Z, B2Y, C3X, D4W, E5V, and F6U are parked around a circular field facing away from the centre. B2Y is parked immediate left ...
Each of six teachers M, N, P, Q, S and I have their classes on six different days of a week starting from Monday and ending on Saturday of the same week...
Which of the following combinations is correct?
Who among the following lives in flat-2 of 4th floor?
B goes for practical exam on which of the following days?