Question
A team of workers can finish a task in 36 days. However, 5
workers leave the task every day, and it gets done in 48 days. Find the time needed for 90 workers to complete the task working together.Solution
ATQ,
Let the number of workers be 'W' and each has efficiency 'e' units/day.
Total work = W × 36 × e = 36We units.
ATQ:
36We = W × e + (W - 5 × 1) × e + (W - 5 × 2) × e + .... + (W - 5 × 47) × e
Or,
36W = 48W - 5 × (1 + 2 + 3 + .... + 47)
⇒ 12W = 5 × 47 × (48/2)
⇒ W = (5 × 47 × 24) ÷ 12 = 470
Let the required time be T days for 90 workers.
So, 36 × 470 × e = 90 × T × e
⇒ T = (36 × 470) ÷ 90 = 188
Which among the following is not a least abundant macronutrients in plants?
The World Meteorological Day is held annually on____
Which of the following is a climber commonly used for vertical gardening and ornamental arches?
Match List-I with List-II and select the correct answer using the codes given below the lists.
Seed certification in India is regulated by:
T and V system, 1974 started by Daniel Benor is also known as
The Ranikhet disease affects:Â
Urea fertilizer is the main source of nitrogen,applied in our fields ,The NPK ratio of urea is:
Which one of the following crop is otherwise known as Kenaf?
Fruit of groundnut is known as