Question
A team of workers can finish a task in 36 days. However, 5 workers leave the task every day, and it gets done in 48 days. Find the time needed for 90 workers to complete the task working together.
More Time and work Questions
- A buffalo alone can plough field ‘A’ in 20 days. A Bull alone can plough the field ‘A’ in 32 days. Find the number of days taken by 2 bulls and 2 buffalo t...
- 40 men or 50 women can build a wall in 30 days. If 40 men and 50 women work together, how many days will they take to complete 60% of the work?
- A and B can finish a task together in '2t' days. B alone can complete the task in 10 days, while A alone can do it in '5t' days. Find the value of 't'.
- In an office, an employee plans to do a work in 12 days with 4 laptops. But after 4 days, he found that only 40% of the work is done with the laptops worki...
- A can do a piece of work in 15 days, B is 25% more efficient than A, and C is 40% more efficient than B. A and C work together for 3 days and then C leaves...
- A can finish a job in 15 days and B can finish the same job in 20 days. In how many days can they finish it working together?
- A team of 15 workers was assigned to complete a task in 30 days. After working together for 20 days, they discovered that only half of the work had been co...
- A cheetah can catch a deer running with a speed of 108 km/h and is 66 meters ahead of it, in 12 seconds. Find the time taken by the cheetah to catch a zebr...
- A buffalo alone can plough field ‘A’ in 20 days. A Bull alone can plough the field ‘A’ in 10 days. Find the number of days taken by 1 bulls and 4 buffalo t...
- A and B can complete a task in 6 days working together. A alone works twice as fast as B. If A works alone for 2 days and B finishes the rest, how many mor...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt