A and B can complete a piece of work in 12 days and 15
days respectively. They start working together, but after 4 days, A leaves. In how many more days will B complete the remaining work?Solution
Work done by A and B in 1 day = (1/12 + 1/15) = 5/60 + 4/60 = 9/60 = 3/20. Work completed by A and B together in 4 days = 4 * (3/20) = 12/20 = 3/5. Remaining work = 1 - 3/5 = 2/5. Work done by B in 1 day = 1/15. Time taken by B to complete 2/5 of the work = (2/5) ÷ (1/15) = (2/5) * 15 = 6 days. Correct Option: a
In hill soils or acidic soils, nutrients are present except?
Which of the given is considered to be of agricultural importance?
The Pusa biodecomposer, a    microbial consortium of fungal species for rapid decomposition of paddy straw has been developed by ______Â
...Lactometer is used to measure _____ in milk.Â
What are tyloses, and what is their role in plant defense against pathogens?
Which of the following tree is incorrectly matched with their common names?
Given below are two statements, one is labelled as Assertion A and the other is labelled as Reason R
Assertion A: The synergistic positive ef...
Late Blight of Potato is caused by
The principal objective of alley cropping is
In C4 plants, the first stable product of photosynthesis is: