Question
A man alone can do a work in 25 days. A woman can complete
half of the same work in 20 days. In how many days can they complete 90% of the work together?Solution
ATQ,
Time taken by the woman to finish the entire work = 20 ÷ 0.5 = 40 days
Let the total work be 200 units. {LCM of (25 and 40)}
So, efficiency of the man = 200 ÷ 25 = 8 units/day
And efficiency of the woman = 200 ÷ 40 = 5 units/day
So, required time = (200 × 0.9) ÷ (8 + 5) = 13.85 days
Which of the following statements given below about the post-Mauryan period is correct?Â
Consider the followingstatements:
1. Charvaka was the main expounder of this philosophy
2. The philosophy is materialistic in nature
National Anthem of India was first sung in the _________ session of Indian National Congress.
The Indian Flag was designed by
In which year, Mahatama Gandhi travelled to struggle against the operssive plantation system?
ONAM is the state festival of?
Where was the Second Buddhist Council convened?
Which of the following features characterize the pre-Mauryan (6th century B.C to 4th century B.C) period in northIndia?
1. Punch marked coins
Who was the founder of the Hoysala Dynasty?
Prolific Indian painter Maqbool Fida Husain predominantly used which of these animals to depict a lively and free spirit in his paintings?