Question
A man alone can do a work in 25 days. A woman can complete
half of the same work in 20 days. In how many days can they complete 90% of the work together?Solution
ATQ,
Time taken by the woman to finish the entire work = 20 á 0.5 = 40 days
Let the total work be 200 units. {LCM of (25 and 40)}
So, efficiency of the man = 200 á 25 = 8 units/day
And efficiency of the woman = 200 á 40 = 5 units/day
So, required time = (200 à 0.9) á (8 + 5) = 13.85 days
âHeart rotâ in Sugarbeet and âwater coreâ in turnip are the deficiency symptoms of:
In plant, the cell walls of ___ cells are coagulated with the deposition of suberin which makes them impervious to water and air.
.................is an international food standards body established with the objective of protecting consumer's health and ensuring fair practices in ...
"Ingredient" means:
Late Blight of Potato is caused by
Name the housing system of poultry envisages the accumulation of the material used for litter with poultry manure until it reaches depth 8-12 inches
The degree of responsiveness between output and input is measured by:
Black soils popularly known as âBlack cotton soilsâ are high in clay content and these soil develop wide cracks during the dry season but their iron...
Litchi mite is controlled by:
Red soil is generally poor in