Question
20 men or 40 women can complete a piece of work in 24
days. A man and a woman together complete the work and receive a total wage of Rs. 12,000. Find the difference between the wages received by them.Solution
ATQ, Let the efficiency of a man and a woman be 'M' and 'W' units/day respectively. We have, 20M × 24 = 40W × 24 So, 20M = 40W Or, (M/W) = (40/20) = 2 Required difference = {(2 - 1) /(2 + 1) } × 12000 = (1/3) × 12000 = Rs. 4,000
What was the retail inflation rate in India in November 2024?
A genetically modified variation of eggplant, named BT-brinjal, has been created. What is the primary objective behind this development?
Which city hosted the Malabar International Naval Exercise 2024?
In which state will the 37th National Games be organized
What is the mass in kgs of the propulsion module utilized in Chandrayaan-3?
What was the primary aim of the significant meeting between India and the UAE about the India-Middle East-Europe Economic Corridor (IMEEC)?
Which company has partnered with PayU to introduce instant credit cards to its Indian users?
Who released the book titled 'Jammu Kashmir and Ladakh: Through the Ages' in January 2025?
Which agency retained India's growth forecast at 6.6% for FY25 (June 2024), making it the fastest growing large economy?
Who has received the ‘Dadasaheb Phalke Lifetime Achievement Award’ for the year 2022?