Question
P can do a piece of work in 15 days, Q can complete
double the work in 40 days and R can do the work in 20 days. If all of them together earn Rs. 3000, then find the money received by Q.Solution
Time taken by P = 15 days Time taken by Q = 20 days Time taken by R = 20 days Let the total work be 60 units. P’s one day work = 4 units Q’s one day work = 3 units R’s one day work = 3 units Amount received by Q = 3000 × (3/10) = Rs. 900
- Who will become the 52nd Chief Justice of India after May 13, 2025, upon government approval?
Indian railways announced for the mission of 100 per cent electrification of its track by the year_______.
The Winter Olympics 2026 are being hosted by which country?
Which startup of India has won Earthshot Prize 2022?
Who addressed the First Alumni meet of the Prerana Program?
According to the latest report of the Stockholm International Peace Research Institute (SIPRI) on Trends in International Arms Transfer 2021, India is _...
The least populated district of India as per 2011 Census is located in which of the following states?
Which of the following is an independent regulator to oversee the auditing profession and accounting standards in India?
The rediscovery of the Asiatic golden cat in Manas National Park, Assam, is seen as a success for which specific organization?
The Government of India and the Asian Development Bank signed a $4.5 million project readiness financing (PRF) loan to support project preparation and d...