Question
Karan and Kavya, alone can complete a work in 16 days
and 24 days, respectively. They started the work together and left after 6 days such that the remaining work is completed by Keshav alone in 6 days. If the total wage fixed for completing the work is Rs. 360, then find the share received by Keshav.Solution
Let total work = 48 units {LCM of 16 and 24} So, efficiency of ‘Karan’ = (48/16) = 3 units/day Efficiency of ‘Kavya’ = (48/24) = 2 units/day Amount of work done by Karan in 6 days = 3 × 6 = 18 units Amount of work done by Kavya in 6 days = 2 × 6 = 12 units Amount of work done by Keshav = 48 – (18 + 12) = 18 units Ratio of amount of work done by Karan, Kavya and Keshav = (18 : 12 : 18) = (3 : 2 : 3) Required wages of Keshav = {3/(3 + 2 + 3)} × 360 = Rs. 135
What agricultural system involves the deliberate use of land for simultaneous agricultural, tree, and forest crop production?
Assuming bulk density and particle density of a soil as 1.5 and 2.5 g/cc, respectively, value of porosity will be:
Strictly self pollinating crop is
Which is not a timber yielding tree species?
In agricultural economics, uncertainties that affect farm outputs due to unpredictable climatic and biological factors are grouped under how many broad ...
Given below are two statements, one is labelled as Assertion A and other is labelled as Reason R
Assertion A: After application of urea in soil, ...
Sterility mosaic in pigeon pea is caused by:
In nutrient uptake studies, which element is primarily associated with the regulation of stomatal movement and enzyme activation?
In the LTLT method of pasteurization, at what temperature is milk exposed for 30 minutes?
Which of the following statements is/are true about soil erosion?
Statement A: Rill erosion is a more severe form of erosion compared to gully er...