Question
A can complete a piece of work in 10 days and B can
complete the same work in 15 days. If both work together, in how many days will the work be completed?Solution
Let total work = LCM of 10 and 15 = 30 units Aβs 1-day work = 30 Γ· 10 = 3 units Bβs 1-day work = 30 Γ· 15 = 2 units Together in 1 day = 3 + 2 = 5 units Time to finish 30 units = 30 Γ· 5 = 6 days Answer: 6 days
Find out the alternative figure which contains figure (X) as its part.
From the given answer figures, select the one in which the question figure is hidden/embedded.
Find out the alternative figure which contains the given figure as its part.
Choose the correct mirror image of the given figure (X) from amongst the four alternatives.


From the given answer figure select the one in which the question figure is hidden/embedded in the same direction.
Select the option in which figure is embedded.
From the given answer figures, select the one in which the question figure is hidden/ embedded.
From the given answer figure select the one in which the question figure is hidden/embedded in the same direction.