Question
40 laborers were hired to finish a construction job in
50 days. After 35 days of work, only 70% of the job was done. How many additional laborers are needed to finish the remaining work in the remaining time?Solution
Let 'x' more laborers are hired. So, according to question: (40 × 35)/0.70 = {(40 + x) × 15}/0.30 40 + x = 93.33 ≈ 94 x = 54 So, 54 more laborers need to be hired to complete the work in time.

If the altitude of an equilateral triangle is 9 cm, then find out its area?
What is the volume of a cylinder if the radius of the cylinder is 17 cm, and the height is 21 cm? (Take π = 22/7)
A rectangular parking space is marked out by painting three of its sides. If the length of the unpainted side is 9 ft, and the sum of the lengths of the...
In a rectangular floor of length and breadth of 20 metres and 4 metres, respectively, square tiles each of 2 metre edge length are to be laid. If the co...
In a rectangular floor of length and breadth of 20 metres and 9 metres, respectively, square tiles each of 3 metre edge length are to be laid. If the co...
- A hollow cylindrical pipe has an inner radius of 8 cm. If the length of the pipe and the thickness of the pipe are 12 cm and 2 cm, respectively, determine ...
The volume of a conical water tank is 4928 m³ and the area of its base is 616 m². Find the length of the canvas required to build the tank if the widt...
Perimeter of a rectangle is 40% more than that of a square of side 40 cm. If difference between length and breadth of the rectangle is 8 cm, then find t...
The ratio of the length of a rectangle, breadth of the rectangle and the diameter of a circle is 10:8:4. If the area of the circle is 154 cm^2 , then wh...