Question
40 laborers were hired to finish a construction job in 50 days. After 35 days of work, only 62.5% of the job was done. How many additional laborers are needed to finish the remaining work in the remaining time?
More Time and work Questions
- Raman can complete a certain task by himself in 30 days. Both Raman and Rajat worked together to finish this task, earning a combined wage of Rs. 5,850. Ou...
- "Bhanu" is 37.5% more productive than "Anurag," the two of them can finish the entire task in 40 days. Determine how long it took "Anurag" by himself to fi...
- 40 men can complete a piece of work in 24 days. All of them started the work together, after 6 days how much more men will be required to complete the same...
- Ashish and Anil can do a piece of work in 12 days and 15 days respectively. Ashish completed 30% of the work. Find the time taken by Anil to complete the r...
- 20 men can complete a piece of work in 40 days. ‘x’ men started the work and after 35 days 64 more men joined them so that whole work was finished in the d...
- Anil, Anshika and Anamika can do a certain piece of work in 64 days, 72 days and 96 days, respectively. All of them started working together but after ___ ...
- ‘A’ and ‘B’ can do a piece of work in 20 days and 30 days, respectively. If they started the work together and worked on it for 7 days, then find the time ...
- ‘A’ alone can complete a work in 40 days while ‘A’ and ‘B’ together can complete the same work in 30 days. How much per...
- 'Ramesh' can complete a work in 40 days. He started the work and left after 24 days from starting. The remaining work was done by 'Suresh' in 30 days. Find...
- A alone can complete 70% of a work in 21 days while B takes 15 days more than A to complete it. If B and C together can complete the work in 20 days, then ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt