πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      40 laborers were hired to finish a construction job in

      50 days. After 35 days of work, only 62.5% of the job was done. How many additional laborers are needed to finish the remaining work in the remaining time?
      A 35 Correct Answer Incorrect Answer
      B 27 Correct Answer Incorrect Answer
      C 16 Correct Answer Incorrect Answer
      D 60 Correct Answer Incorrect Answer

      Solution

      Let the total work be W.

      40 laborers working for 35 days completed 62.5% of the work.

      So,

      40 Γ— 35 = 1400 laborer-days = 62.5% of W

      62.5% = 5/8

      So,

      5/8 of W = 1400

      W = 1400 Γ— 8/5 = 2240 laborer-days

      Remaining work = 100% - 62.5% = 37.5% of W

      37.5% = 3/8

      Remaining work = 3/8 Γ— 2240 = 840 laborer-days

      Time left = 50 - 35 = 15 days

      Number of laborers needed to finish 840 laborer-days in 15 days:

      840 Γ· 15 = 56 laborers

      Additional laborers needed = 56 - 40 = 16

      Answer:

      16 additional laborers are needed.

      Practice Next

      Relevant for Exams:

      ask-question