Question
Chacha and Bhatija can complete a work in 48 days. In how many days Chacha alone does the 2/3rd of the total work if they start working together after 40 days Chacha left the work, work is completed in 52 days.
More Time and work Questions
- P does one fourth as much work as Q in two third of the time. If together they take 24 days to complete the work, how much time shall Q take to do it?
- 55 men can complete a piece of work in 18 days. ‘x’ men started the work and after 9 days 64 more men joined them so that whole work was finished in the de...
- A can complete a piece of work in 12 days , and B can complete it in 18 days . They work together for 4 days , and then A leaves. In how many more days...
- Meena alone can complete a work in 20 days. Ritu is twice as efficient as Meena. Find the percentage of work completed by Meena and Ritu together in 4 days...
- 'X' can complete 75% of a work in 15 days, whereas 'Y' can complete 25% of the same work in 10 days. They both started working together, but 'Y' left the j...
- The ratio of the efficiency of A, B and C is 3:4:5, if they can complete a work in 18 days then A can complete 60% of the work in how many days?
- A and B can complete a job together in 30 days; B and C can complete the same job together in 25 days, while C and A can complete the same job together in ...
- Raman can complete a certain task by himself in 30 days. Both Raman and Rajat worked together to finish this task, earning a combined wage of Rs. 5,850. Ou...
- 48 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for 48 ...
- Shudhanshu completes 1/2 of work in 12 days, then he completes the remaining work with the help of Neeraj in 5 days. The time required for Sudhanshu and N...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)