Question
Chacha and Bhatija can complete a work in 48 days. In
how many days Chacha alone does the 2/3rd of the total work if they start working together after 40 days Chacha left the work, work is completed in 52 days.Solution
=> 1/Chacha + 1/Bhatija = 1/48 If, Chacha leaves the work after working 40 days with Bhatija, then the whole work is completed in 52 days. Therefore, Bhatija alone works for 12 days. => 40 (1/Chacha + 1/Bhatija) + 12/Bhatija = 1 => (40 × 1/48) + 12/Bhatija = 1 => 5/6 + 12/Bhatija = 1 => 12/Bhatija = 1 – 5/6 => 12/Bhatija = 1/6 => Bhatija = 72 Then, 1/Chacha = 1/48 – 1/72 => Chacha = 144 Chacha alone can complete the whole work in 144 days. And, Chacha can do 2/3rd of the work in = (144 × 2/3) days = 96 days.
What is the target Fiscal Deficit as a % of GDP for FY23 in the Union Budget 2022-23?
A ______ is a document from a bank guaranteeing that a seller will receive payment in full as long as certain delivery conditions have been met.
Which of the following most likely increases the wealth of shareholders?
Recently which public sector lender has rolled out six new digital initiatives under ‘Project WAVE’ for enhancing customer experience throug...
Central government has extended the decision to keep ‘free-import’ policy for two varieties of tur and urad by _____.
Bank of Maharashtra reported a _______per cent jump in its standalone net profit at Rs 165 crore in the quarter ended March 31, 2021.
What was the projected GDP growth rate for India in FY25 according to India Ratings and Research?
Which of the following banks has listed its USD 1 billion additional tier- I (AT-1) bonds on the IFSC (International Financial Services Centre) exchange...
Which kind of following financial instruments can be issued by Non-Profit Organizations as per the framework provided by SEBI for Social Stock exchanges...
Reserve Bank of India has launched the Inflation Expectations Survey of Households (IESH) which will provide useful inputs for?