Question
120 unit of work can be completed by P alone in 20 days.
P started working alone and joined by Q after 10 days such that they completed the remaining work in 6 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (120/20) = 6 units/day According to question: 6 × 10 + (6 + x) × 6 = 120 Or, 60 + 36 + 6x = 120 Or, 6x = 120 – 96 Or, 6x = 24 Or, x = 4 Number of days taken by Q to complete the work alone = (120/4) = 30 days
Which of the following Statements about Multiplier Effect is/are True?
I- When the government spends a rupee, overall income rises by a multiple ...
Consider the following statements regarding Phase II of the Swachh Bharat Mission (Grameen) [SBM (G)]
1) The program will be implemented...
What is the basic difference between Gross NPA and Net NPA?
I- Gross NPA is the total of Bank loans and Net NPA is the total of all kinds of loan...
Which of the following Statements about IREDA is/are True?
I- It is registered as Non-Banking Financial Company (NFBC) with Reserve Bank of India...
When Government expenditure is more than income, through which of the following ways, it does the deficit financing?
(1) From Banks
(2) Fr...
Which of the following statements about Prompt Corrective Action is/are True?
I- Prompt Corrective Action F...
Who among the following is not one of the eligible beneficiaries of PMUY?