Question
120 unit of work can be completed by P alone in 20 days.
P started working alone and joined by Q after 10 days such that they completed the remaining work in 6 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (120/20) = 6 units/day According to question: 6 × 10 + (6 + x) × 6 = 120 Or, 60 + 36 + 6x = 120 Or, 6x = 120 – 96 Or, 6x = 24 Or, x = 4 Number of days taken by Q to complete the work alone = (120/4) = 30 days
The National Mission on Edible Oils – Oilseeds (NMEO-Oilseeds) aims to boost oilseed production in India. Which key oilseed crop is not included in t...
Which of the following states/UT has tied up with UNDP(United Nations Development Programme) to build an oxygen producing facility there?
What term will India serve on the UN Peacebuilding Commission (PBC) after re-election in 2025?
Chief Minister Yuva Swarozgar Yojana was launched in which of the following year in Uttar Pradesh?
Who has received the ‘Patangrao Kadam Award’?
Kuchipudi is a classical dance form originating from which Indian state?
Switzerland Tourism has roped which of the Indian athletes as its Friendship Ambassador recently?
The 12th Joint Working Group (JWG) on Border Management meeting is held on 15th and 16th June, 2022 between India and which other country?
Till March 2024, what was the GST collection of Haryana state?
Which of the following terrains is known as older alluvial deposits?