📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      A can finish a piece of work in 12 days, B in 15 days.

      They work together for 4 days, then A leaves and C joins B. C is 25% more efficient than B. In how many total days will the work be finished?
      A 15/7 days Correct Answer Incorrect Answer
      B 20/3 days Correct Answer Incorrect Answer
      C 25/8 days Correct Answer Incorrect Answer
      D 12/5 days Correct Answer Incorrect Answer

      Solution

      A = 1/12, B = 1/15 per day. In 4 days: Work done = 4 × (1/12 + 1/15) = 4 × (9/60) = 0.6. Remaining = 0.4. C = 1.25 × (1/15) = 1/12. B + C = 1/15 + 1/12 = 7/60. Time for remaining = 0.4 ÷ (7/60) = 24/7 = 8/3 days. Total = 4 + 8/3 = 20/3 days.

      Practice Next

      Relevant for Exams:

      ask-question