      Question

      35% of the work done by Sunil in 8 days is equal to 70% of the work done by Raj in 3 days. If Sunil alone can do the work in 24 days, find the number of days Raj would need to finish the work.

      A 45 days Correct Answer Incorrect Answer
      B 40 days Correct Answer Incorrect Answer
      C 20 days Correct Answer Incorrect Answer
      D 28 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let the efficiency of Sunil and Raj be 'x' units/day and 'y' units/day respectively.

      So, 0.35 Γ— x Γ— 8 = 0.7 Γ— y Γ— 3

      So, x = (21/8) Γ— y

      Total work = 24 Γ— x = 24x units

      Time taken by Raj to complete the work:

      = (24x / y) = {24 Γ— (21/8) y} Γ· y = 63 days