‘X’ can finish a task in 36 days, while ‘X’ and ‘Y’ together can do it in 18 days. If ‘Y’ worked alone for 20 days and then left, how many days will ‘X’ take to complete the remaining work?

A 25 days
B 40 days
C 10 days
D 16 days