Question
Consider that 'A' and 'B' were collectively paid Rs.
9,000 for a job. Out of this amount, 'B' received Rs. 3,000. If 'B' can finish this task solo in 48 days, determine the duration it would take for 'A' to complete the work independently.Solution
Ratio of efficiency of A:B = (9000 – 3000):3000 = 2:1 So, ratio of the time taken by ‘A’ alone to complete the work and ‘B’ alone to complete the same wor, respectively = 1:2 Therefore, time taken by ‘A’ alone to complete the work = 48/2 = 24 days
What is the primary advantage of using CIDR (Classless Inter-Domain Routing) in IP addressing?
Which of the following is the most critical factor for implementing predictive analytics in the finance industry for risk modeling?
In time series analysis, which component is best described as the long-term movement in data values that is not affected by seasonal or random fluctuati...
Which of the following transformations is most appropriate to bring all feature values into the range [0,1] for a machine learning model?
...Which of the following statements correctly identifies the components of time series data ?
Which condition must be satisfied for Kruskal’s Algorithm to function correctly?
Which of the following is an example of non-random sampling?
Which of the following methods is most appropriate for forecasting future values in time series data with a consistent trend and seasonality?
If a dataset has a strongly skewed distribution , which measure of central tendency is most appropriate to represent the data?
You are combining sales data from three different sources, each with slightly different column names for the same information (e.g., "Product_ID," "Prod...