📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      C is 50% more efficient than D and can complete a task in

      18 days. C and D work together for 6 days, after which D leaves. In how many more days will C finish the rest of the task?
      A 12 days Correct Answer Incorrect Answer
      B 8 days Correct Answer Incorrect Answer
      C 10 days Correct Answer Incorrect Answer
      D 21 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ,

      Time taken by D to complete the work = 1.5 × 18 = 27 days

      Let the total work be 108 units

      Efficiency of C = 108/18 = 6 units/day

      Efficiency of D = 108/27 = 4 units/day

      Work completed in 6 days = (6 + 4) × 6 = 60 units

      Remaining work = 108 - 60 = 48 units

      Therefore, x = 48 / 6 = 8 days

      Practice Next
      ask-question