Question
A and B are capable of completing a project individually
in 40 days and 50 days, respectively. Initially, A and B collaborated on the project, and after 10 days, C joined them. With C's assistance, the total project was completed in 20 days. How long would it take for C to complete the project on their own?Solution
Part of the work done by A and B in one day = (1/40) + (1/50) = 9/200 Part of the work done by A and B in 10 days = 90/200 Remaining work = 1 β (90/200) = 110/200 Let the time taken by C alone to complete the work be βcβ days. So, (90/200) + (10/c) = 110/200 10/c = (110/200) β (90/200) c = 100 So, time taken by C alone to complete the work = 100 days
Identify the figure given in the options which when put in place of β?β will logically complete the series.
Β 'A + B' means 'A' is the sister of 'B'.
'A @ B' means 'A' is the wife of 'B'.
'A $ B' means 'A' is the son of 'B'.
'A % B' means ...
A unique number has been assigned to each letter in the following table. Select such a combination of numbers which when arranged according to the lette...
Sumantra starts from Point Y and drives 11 km towards the South. He then takes a left turn, drives 27 km, turns right and drives 39 km. He then takes a ...
Four pairs of letter-clusters have been given, out of which three are alike in some manner and one is different. Select the one that is different.
Select the option figure in which the given figure is embedded (rotation is NOT allowed).
Study the given pattern carefully and select the number that can replace the question mark (?) in it.
The sentence below has a word in which the letters are jumbled up. Rearrange the letters of that word, written in capital letters, to form the correct w...
A is 25 years younger than B. The age of B would be double the age of C after 15 years. The current age of B is three times the current age of C. What i...
Select the option that is related to the third word in the same way as the second word is related to the first word.(The words must be considered as mea...