Question
A and B together can complete a task in 12 days, while A
alone can complete the same task in 20 days. If A and B start the work together, but B leaves after 8 days, in how many more days will A complete the remaining work?Solution
Work done by A and B in 1 day = 1/12 Work done by A alone in 1 day = 1/20 Work done by B in 1 day = 1/12 - 1/20 = 1/30 Work completed in 8 days by A and B = 8 × 1/12 = 2/3 Remaining work = 1 - 2/3 = 1/3 Time taken by A to complete remaining work = (1/3) ÷ (1/20) = 20/3 = 6.67 days. Correct answer: a) 6.67 days
Inflorescence type present in Cashew crop isÂ
ECR stands for............................?
Which of the following is a Rabi crop?
Which state is the highest producer of chili and turmeric?
Caruncle is found in the seed of:
Which natural fiber is also known as the "golden fiber"?
Black heart, a physiological disorder, is associated with which crop?
In Diptera (flies), what term refers to the modified hind wings used primarily for maintaining balance during flight?
Which rootstock is extensively used in North India for citrus propagation?
Rocks containing free silica in abundance and is not combined with bases are called