Question
A and B together can complete a task in 12 days, while A
alone can complete the same task in 20 days. If A and B start the work together, but B leaves after 8 days, in how many more days will A complete the remaining work?Solution
Work done by A and B in 1 day = 1/12 Work done by A alone in 1 day = 1/20 Work done by B in 1 day = 1/12 - 1/20 = 1/30 Work completed in 8 days by A and B = 8 × 1/12 = 2/3 Remaining work = 1 - 2/3 = 1/3 Time taken by A to complete remaining work = (1/3) ÷ (1/20) = 20/3 = 6.67 days. Correct answer: a) 6.67 days
What is the purpose of puddling done in paddy cultivation?
Which term describes the process where water vapour is released from plant leaves into the atmosphere?
Nucleic acids are:
The opening on an arthropod body surface that allows for air transfer is called:
Quality protein maize is rich in
Albugo candida survives as
Which one is an example for nonselective herbicide?
Khaira disease in rice field is due to the deficiency of which of the following nutrient?
Choose the wrong statement.
Given below are two statements:
Statement I: Law of diminishing return also regarded as a fundamental law in agriculture and economics.
St...