Question
A and B together can complete a task in 12 days, while A
alone can complete the same task in 20 days. If A and B start the work together, but B leaves after 8 days, in how many more days will A complete the remaining work?Solution
Work done by A and B in 1 day = 1/12 Work done by A alone in 1 day = 1/20 Work done by B in 1 day = 1/12 - 1/20 = 1/30 Work completed in 8 days by A and B = 8 × 1/12 = 2/3 Remaining work = 1 - 2/3 = 1/3 Time taken by A to complete remaining work = (1/3) ÷ (1/20) = 20/3 = 6.67 days. Correct answer: a) 6.67 days
In a certain coded language PURPLE is coded as TXRGOR, then how is POLITY coded in that coded language?
According to the given code, find the code word of ‘experience similar soldier definition’?
In a certain code, 'MANGO' is coded as ‘250’. Then how will ' ORANGE ' be written in that code?
Unscramble the following letters to frame a meaningful word, then find out the correct numerical position of the letters:
In a certain language,
'pl zs ls' means 'conspiracy was hatched',
'uq al bg' means 'would replace him'
'bg kr ls' means ‘him as h...
In a certain code language, ‘GEAR’ is written as ‘62’ and ‘RAIN’ is written as ‘84’. How will ‘SHOT’ be written in that code langua...
What is the code for the word ‘silence situation’?
If in a certain coding language, ‘PERFORMANCE’ is written as ‘81’, how will ‘PLATFORM’ be written using the same code?
In a certain code language, ‘BUTTER’ is coded as ‘CWWSCO’ and ‘THEORY’ is coded as ‘UJHNPV’. How will ‘LATENT’ be coded in that lang...
If ‘ANKLET’ is coded as ‘EJGHIP’ and ‘APPLY’ is coded as ‘ELLHU’, then ‘DRIVER’ will be coded as ____ in the same code language.
...