Question

A and B together can complete a task in 12 days, while A alone can complete the same task in 20 days. If A and B start the work together, but B leaves after 8 days, in how many more days will A complete the remaining work?

A 6.67 days
B 5.5 days
C 6.5 days
D 7 days