Question
A, B, and C can finish a work in 12, 15, and 20 days,
respectively. They all start working together, but A leaves after 4 days, and B leaves after 1 more days. How much longer will C take to finish the remaining work?Solution
Work done by A in 4 days = 4 / 12 = 1/3. Work done by B in 5 days = 5 / 15 = 1/3. Total work done by A and B = 1/3 + 1/3 = 2/3. Remaining work = 1 - 2/3 = 1/3. Work done by C per day = 1/20. Time taken by C to finish 1/3 work = (1/3) / (1/20) = 20 / 3 = 6.67 days But since 5 days he was working with them, which means he will take extra = 6.67 – 5 = 1.67 days Correct answer: a) 1.67 days.
How did Indian cities rank in Global Financial Centres Index (GFCI) 33?
Which of the following initiatives are launched by the government of India to tackle climate change and the environment?
1.   LIFE– Life...
Consider the following Statements about the GFCs and choose the option with Correct Statements.
I- The city ranked as the No. 2 GFC in the world ...
Which is the biggest International Financial Services Centres in the globe?
Consider the following statements in regards to the Economic Survey of India 2022-23:
1.India became the second-largest mobile phone manufacturer...
A Banking Unit shall follow Know Your Customer norms, combating of financing of terrorism and other anti-money laundering requirements, including report...
The subprime lending meltdown in 2008 made the banks and regulators realize the importance of liquidity risk management in banks. Which of the following...
What is the primary objective of the Insolvency and Bankruptcy Code (IBC), 2016?
Which is the largest International Financial Services Centres in Asia?
Which insurance companies have partnered with Policybazaar to develop the health, wealth, and life solution?