Question
‘A’ and ‘B’, alone can complete a work in 25 days and 50 days, respectively. Both of them started the work together but ‘A’ left the work when 2% of the work was remaining which is then completed by ‘B’ alone, then find the total time required to complete the whole work in this way.
More Time and work Questions
- P alone can finish a piece of work ‘M’ in 8 days while Q takes 4 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 7 ti...
- A is 20% more efficient than B. How much time will they working together take to complete a job which A alone could have done in 29 days?
- ‘A’ takes 6 days less than ‘B’ to complete a work. ‘B’ can complete 1/5th of the work in 6 days. Both of them started the work together and worked for 8 da...
- 15 men can finish a work in 16 days by working 6 hours a day. How many more men are needed to finish the work in 10 days by working 8 hours a day?
- Ashish and Anil can do a piece of work in 18 days and 24 days respectively. Ashish completed 25% of the work. Find the time taken by Anil to complete the r...
- If ‘X’ finishes a project in 24 days whereas ‘X’ and ‘Y’ working together can finish it in 15 days, then determine the time ‘Y’ alone will take to finish t...
- Aman can complete a task in 12 days, while Bhanu alone can complete the same task in 18 days. Aman starts the work alone and continues for 4 days. Then, Bh...
- 40 men can complete a piece of work in 24 days. All of them started the work together, after 6 days how much more men will be required to complete the same...
- A can complete a piece of work in 12 days , and B can complete it in 18 days . They work together for 4 days , and then A leaves. In how many more days...
- ‘A’ can complete a work in 18 days and is 10% more efficient than ‘B’. ‘A’ and ‘B’ start the work together, but ‘A’ leaves after 15 days. The remaining wor...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
days Number of days taken by ‘B’ to complete 5 units of the work = (5/5) = 1 day Total time taken to complete the work =
+ 1 =
day