Question
βAβ can do a piece of work in 12 days. βBβ can
do 70% of the same work in 30 days. If they work together for the entire time and get paid Rs.1504, then find the share of βAβ.Solution
Let the total work be 60 units. (LCM of 12 and 30) Efficiency of A = 60/12 = 5 units/day Efficiency of B = (60/30) Γ (70/100) = 7/5 units/day Ratio of the efficiency of A : B = 5 : 7/5 = 25:7 Share of A = (25/32) Γ 1504 = Rs.1175
Who spearheaded the Bardoli Satyagraha in 1928, a key event in India's fight against colonial taxation?Β
Justice Miller Committee was related to which of the following aspects?
The First Anglo-Burmese War was concluded with which treaty?
The Quit India Movement was launched in which year?
Consider the following movements and arrange them in chronological order:
1. Eka Movement.
2. Tebhaga Movement.
3. Bardoli S...
Consider the following statements with reference to the βUlgulanβ:
1. It occurred in the Chotanagpur region.
2. Chakra Bisoi was th...
The East India Company was set up on the banks of the river _____ in 1651.
Who was the Viceroy of India when the Indian Factory Act of 1891 was passed?
Which emperor wrote the Sanskrit play 'Nagananda'?
Consider the following statements regarding the Alipore Bomb Conspiracy Case, 1908:
1. Revolutionaries who threw the bomb were Prafulla Chaki and...