Question
βAβ can do a piece of work in 12 days. βBβ can
do 70% of the same work in 30 days. If they work together for the entire time and get paid Rs.1504, then find the share of βAβ.Solution
Let the total work be 60 units. (LCM of 12 and 30) Efficiency of A = 60/12 = 5 units/day Efficiency of B = (60/30) Γ (70/100) = 7/5 units/day Ratio of the efficiency of A : B = 5 : 7/5 = 25:7 Share of A = (25/32) Γ 1504 = Rs.1175
Which sources of funding are typically available to Self-Help Groups (SHGs)?Β Β
In the Budget 2022 -23, Finance Minister Nirmala Sitharaman has allocated how much fund to the Jal Jeevan Mission?
When is the World's Children Day been celebrated?
Consider the following statements:
1.The Pradhan Mantri Awas Yojana- Gramin (PMAY-G) had been devised in line with Government's commitment to pro...
The term βBack-stickβ is used in which of the following games/sports?
How many technology innovation platforms have been launched by the Central Government for development of technologies for globally competitive manufactu...
Which Ladakhi dance has created history by breaking into the Guinness book of world records as the largest Ladakhi dance?
Which of the following countries has been warned of a cholera outbreak by the UNICEF?
In which Indian state, specifically at the historic excavation site, have archaeologists unearthed a crystal quartz used as a weighing unit dating back ...
How many companies were amalgamated and grouped into four major insurance companies?Β