‘A’ can do a piece of work in 8 days. ‘B’ can do 40% of the same work in 16 days. If they work together for the entire time and get paid Rs.1500, then find the share of ‘A’.

A Rs.1175
B Rs.1250
C Rs.720
D Rs.1000