Question
βAβ can do a piece of work in 10 days. βBβ can
do 80% of the same work in 12 days. If they work together for the entire time and get paid Rs.1200, then find the share of βAβ.Solution
Let the total work be 60 units. (LCM of 10 and 12) Efficiency of A = 60/10 = 6 units/day Efficiency of B = (60/12) Γ (80/100) = 4 units/day Ratio of the efficiency of A : B = 6 : 4 = 3:2 Share of A = (3/5) Γ 1200 = Rs.720
What is the largest three-digit number that leaves a remainder of 5 when divided by both 11 and 13? Call this number a. Additiona...
A positive number becomes 34 times its reciprocal if 9 is subtracted from it. Find the number.
- Find the largest 5-digit number that is completely divisible by β52β:
Find the least 4-digit number which, when divided by 18, 30, and 45, leaves a remainder of 2 in each case.
A = (9/4) Γ B and C = (1/12) Γ A. If (A + B + C) = 300, then find the value of (12C β B).
X is 10 ft tall, and he notices that he casts a shadow that's 3 ft long. He then measures that the shadow cast by his school building is 30 ft long. How...
A waiter income consist of his salary and tips. During one week his tips were 4/5 of his salary. What portion of his income came from tips?
The following dataset represents the examination scores achieved by 10 students:
36, 91, 80, 77, 64, 80, 45, 56, 41, 96
Find the median of...
When a number is divided by 17, the remainder remains 6. Find the remainder obtained when the square of the same number is divided by 17.
Two numbers add up to 18, and the sum of their reciprocals is 5/2. Calculate the square of the product of the two numbers.