Question
‘A’ can do a piece of work in 10 days. ‘B’ can
do 80% of the same work in 12 days. If they work together for the entire time and get paid Rs.1200, then find the share of ‘A’.Solution
Let the total work be 60 units. (LCM of 10 and 12) Efficiency of A = 60/10 = 6 units/day Efficiency of B = (60/12) × (80/100) = 4 units/day Ratio of the efficiency of A : B = 6 : 4 = 3:2 Share of A = (3/5) × 1200 = Rs.720
There is a rectangular paper, whose length and breadth are in the ratio 13:17, respectively and it has a perimeter of 120 metres. If a triangular piece ...
The Height of a metallic hollow cylinder is 28 cm and the difference between its inner curved surface Area and outer curved Surface area is 66cm². If t...
The height of a right circular cone is 18 cm. If the volume of the cone is 4158 cm³, find the ratio of the height of the cone to...
- Seven cubes, each of edge 7 cm, are attached in a row to make a cuboid. Find its total surface area.
A right circular cylinder having total surface area of 44352 cm2 is immersed in a vessel completely filled with water. If the height of the c...
A pipe fills a cubical tank at the rate of 242 m3Â per minute in 44 minutes. If a cylindrical tank having height same as the side of a cubica...
If the sides of a triangle measure 21 cm, 35 cm and 28 cm, what is the measure of its in radius? (in cm)
In the given figure, a circle is inscribed in Δ PQR, such that it touches the sides PQ, QR and RP at points D, E, F, respectively. If the lengths of th...
A cone and a hemisphere have the same base radius and the same height. If the total volume of both is 2,160 cm³, find the radius.
A solid rectangular parallelepiped (cuboid) has dimensions 10 cm × 8 cm × 6 cm. It is melted and cast into small cubes each of side 2 cm. How many suc...