Question
‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 12 days. If they work together for the entire time and get paid Rs.1200, then find the share of ‘A’.
More Time and work Questions
- ‘P’ and ‘Q’ together can finish a task in 15 days while ‘Q’ alone can do it in 25 days. If the ratio of efficiencies of ‘P’ and ‘R’ is 3:5 respectively, th...
- Rahul alone can do 60% of the same piece of work in (z-4) days. Queen and Rahul together can do 75% of the same piece of work in (0.5z+4) days. Pankaj alon...
- A man, a woman and a boy can do a work in 4, 8, 16 days respectively. How many boys were required with 1 man and 1 woman to complete the same work in 1/2 d...
- ‘R’ and ‘S’ together can finish a work in 25 days. If ‘R’ increases his efficiency by 60% and ‘S’ decreases his efficiency by 20%, then the time taken rema...
- A is half as efficient as B. C does half as much work as A and B together. If c alone can do the work in 40 days. Then in how many days will A, B and C tog...
- 1 man and 4 women can complete a work in 65 /4 days, while 3 men and 4 women can complete it in 13 /2 days. In whom many days will be 13 women complete the...
- 50 men can complete a piece of work in 10 days. ‘x’ men started the work and after 5 days 60 more men joined them so that whole work was finished in the de...
- Mira is 40% more efficient than Priya, and Neha is 10% more efficient than Mira. If Neha and Mira together can do a piece of work in 15 days, in how many d...
- A and B together, B and C together and A and C together can complete a piece of work in 14 days, 15 days and 18 days respectively. Find the ratio of the ef...
- ‘n’ men working 20 hours a day can complete a work in 8 days while (6n – 4) men working 10 hours a day can complete the same work in 8 da...