Question
Rahul can complete a work in 12 days and Ayush in 15
days. If they work together for 3 days, then the fraction of work that will be left is:Solution
Let us assume total work to be L.C.M(12,15) be 60 unit (you can assume any number but for the sake of calculation it is advised to take L.C.M of the given numbers) Â Efficiency of Rahul = 60/12 = 5 unit/day Efficiency of Ayush = 60/15 = 4 unit/day Total efficiency of Rahul and Ayush = 5 + 4 = 9 unit/day According to the question, They work together for 3 days Total work done = 9 x 3 = 27 unit Remaining work = (60-27) = 33 unit Fraction of remaining work = 33/60 =11/20
Given below are six sentences, four of which (P, Q, R, S), are jumbled. Pick the option that gives the correct order of P, Q, R, S.
S-1 We have s...
Given below are six sentences 4 of which are jumbled. The first and the last sentence are given. Pick the option that gives the logically correct order ...
Given below are four jumbled sentences. Select the option that gives their correct order.
A. When the convicts were led out to work, the convoy s...
Given that 1 is the first sentence, which of the following will be the FIFTH sentence after rearrangement?
Which of the following would be the FIFTH statement after rearrangement?
Given below are five jumbled sentences. Select the option that gives their correct logical sequence.
A: While the exact cause is debated, some...
The question consists of five statements labelled A, B, C, D and E which when logically ordered form a coherent passage. Choose the option that represe...
Given below are four jumbled sentences. Out of the given options pick the one that gives their correct order.
A. Later, they set up their own art...
Sentences of a paragraph are given below in jumbled order. Arrange the sentences in the correct order to form a meaningful and coherent paragraph.
...Given below are a few sentences in which four words are emboldened each. The words may or may not be in their correct position. Rearrange the words if ...