      Working alone, B can complete the work in 25 days. C is

      twice as efficient as B and A takes 2.5 days more than it takes C to complete the work. Working together, in how much time would they be able to complete 14 such works?
      A 70 days Correct Answer Incorrect Answer
      B 48 days Correct Answer Incorrect Answer
      C 87 days Correct Answer Incorrect Answer
      D 63 days Correct Answer Incorrect Answer
      E 75 days Correct Answer Incorrect Answer

      Solution

      Time taken by B to complete the work = 25 days
      Time taken by C to complete the work = 25/2 = 12.5 days
      Time taken by A to complete the work alone = 12.5 + 2.5 = 15 days
      Work done by A, B and C together in 1 day.
      ⇒ (1/25 + 1/12.5 + 1/15) = (12 + 24 + 20)/300 = 56/300
      this means if would take 300/56 days for A, B and C to complete the work together
      ∴ Time taken A, B and C to complete 14 works = 14 × 300/56 days = 75 days