Question
6 interns together do as much work as a regular employee.
If 36 interns finish 90 tasks in 3 days, how many regular employees are required to do 90 tasks in 2 days?Solution
ATQ,
Let the efficiency of each intern be 'x' units/day
Efficiency of each employee = 6x units/day
Let the number of employees be 'm'
(36x Γ 3)/90 = (6x Γ m Γ 2)/90
β 12m = 108
β m = 9
Therefore, 9 regular employees are required to do the work in 2 days.
A wide variety of living organisms is called
Which plant is used for indication of permanent wilting point?
The ______________ is a unique institution under ICAR to conduct research and training in agricultural management
TRIPS (Trade-Related Aspects of Intellectual Property Rights) agreement is administered by the _______ .
Sea island cotton is known as:
Photosynthetic pathway is a critical factor to consider, particularly since many of the world's most problematic weeds are:
Use of microorganisms to remove or detoxify pollutants, usually as contaminants of soils, water or sediments that otherwise intimidate human health is k...
The degree of unsaturation of lipids can be measured as
Sunhemp should be planted at what distance (in cm) to raise fibre crop?
Which crop protection strategy helps in avoiding continuous cropping or monoculture and is effective in controlling root diseases by varying the planted...