📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      'B' and 'C' in a team can complete a piece of work in 25

      days and  on other hand 'B' alone can do the same work in 40 days. If they started the work in a team and after 10 days 'B' left, then What will be the time taken by 'C' alone to complete the remaining work.
      A 40 days Correct Answer Incorrect Answer
      B 45 days Correct Answer Incorrect Answer
      C 35 days Correct Answer Incorrect Answer
      D 25 days Correct Answer Incorrect Answer
      E none of these Correct Answer Incorrect Answer

      Solution

      Let the entire work will be  = (LCM of 40 and 25) = 200 units The efficiency of 'B' = (200)/(40) = 5 units/day The efficiency of 'B' and 'C' together = (200)/(25) = 8 units/day Then, efficiency of 'C' = 8 - 5 = 3 units/day Let‚ 'C' worked alone for 'd' days ATQ, we can say that  8 x 10 + (3 x d) = 200 Or, 3d = (200 - 80) = 120 Or, d = 120/3 = 40 Therefore, 'C' can complete the remaining work in 40 days

      Practice Next

      Relevant for Exams:

      ask-question