Question
'Sumit' can complete (3/8) of a job in 24 days, where as 'Sumit' and 'Tarun' together can finish it in 16 days. Calculate the time 'Tarun' needs to complete 60% of the job alone.
More Time and work Questions
- Amit', 'Bhanu', and 'Chintu' can finish a piece of work in 51 days, 85 days, and 102 days respectively. They all begin working together on the task, but 'B...
- A can finish a piece of work in 12 days and B can finish it in 18 days. They work together for 4 days, after which B leaves. In how many more days will A c...
- A and B together can complete a work in 10 days. B and C together can do it in 12 days, and A and C together can do it in 15 days. In how many days will al...
- A and B can finish a piece of work in 20 days and 30 days respectively. Both work on alternate days. In how many days will the work be completed when A sta...
- Karan, Arjun and Krunal alone can complete a work in 35, 70 and 60 days respectively. All of them started working together but after 3 days from start Kara...
- There is enough food in a camp to last for 30 days if each of the 60 soldiers present at the camp eat 4 times a day. After 12 days, 12 more soldiers joined...
- ‘X’ and ‘Y’ together can do a work in 16 days. If ‘X’ increases his efficiency by 75% and ‘Y’ decreases his efficiency by 25%, then the time taken to compl...
- ‘A’ alone can complete a work in 40 days while ‘A’ and ‘B’ together can complete the same work in 30 days. How much per...
- ‘P’, ‘Q’ and ‘R’ can finish a task in 12 days, 36 days and 72 days respectively. ‘P’ and ‘Q’ begin the task. After ‘n’ days, ‘P’ leaves and ‘R’ joins ‘Q’. ...
- Vijay can do a piece of work in 10 days and Sanjay can do the same work in 15 days. If Vijay works for 4 days and got Rs. 1680, and the remaining work will...