βPβ and βQβ can complete a task together in 30
days. If βPβ is 60% more efficient than βQβ, how many days will βQβ take to finish the work alone?Solution
Let the efficiency of βQβ be 10x units. Efficiency of βPβ = 10x Γ 1.6 = 16x units Total work = 30 Γ (10x + 16x) = 780x units Time taken by βQβ alone = 780x Γ· 10x = 78 days
What is the definition of "inflation" in economic terms?
Who has been selected as the brand ambassador of NMDC recently?
An increase in savings in an economy typically leads to which of the following?Β
The annual rate of growth of GDP has been the lowest in which Five Year Plan?
Which of the following statements is true?
I. The capital market is a market for securities (debt or equity), where companies and Government ca...
Which of the following is true regarding GDP?
i. In calculating GDP only final marketable goods and services are considered
ii. GDP can be...
Which country's stock exchange is indexed by 'Bovespa'?
Who heads the National Development Council (NDC)?
Which of the following best describes inflationary pressure in an economy?Β
What does the economic term 'Cross Demand' relate to?